Building Department > Permit Information: Commercial/Industrial |
 |
Commercial/Industrial New Constructions and Alterations
I. Required Permits
- City Permits:
- Site (include plot of survey)
- Structure
- Electrical
- Plumbing
- Mechanical
- Sprinklers/Alarm
- Other Commercial
- Water Reclamation - Sewer (if new connection) (312) 751-5600
- IEPA - Water (if new connection) (217) 782-1724
- Other
- Fee for new sewer and water connections
Leyden Township $650
Proviso Township $750
Note:
It is preferred that permits be issued at all one time, but the city will permit in phases such as
site work, foundations, electrical etc. But no permit will be issued until subcontractors for that phase
are licensed with the city. (See V. Contractors below)
II. Plan Review
- Submit four sets of stamped plans (include use group type, and material list of stock)
- Time Frame:
- 1st review should be completed in about 15 working days. All comments
will be forwarded to the general contractor, and architect or engineers.
- 2nd review should be completed in about 15 working days after receipt of correction sheets.
- If additional reviews are needed, plan on about a 15 working day turnover.
III. Whose Who
- Christopher Burke Engineering - Site Plan review
- IIL Independent Inspections - Architectural, etc. review
- Dale Roberts - Public Works - water and water meters - (708) 562.0940
- Ted Handrock - IIL Building Inspector - (708) 343.8700
- Marybeth - Building Dept. - coordinator - (708) 343.8700
IV. Inspections
- 24 hours notice on all inspections
V. Contractors
- All contractors must be licensed with the City of Northlake including general and all subs.
- Contractor Requirements:
|